The layout of the interior of the lower level and performance space is now clear to see. Steel studs for interior walls are up everywhere, thanks to Montgomery / Timmerman Construction.
Elite Plumbing has been working hard at getting the plumbing needs taken care of, and the electrical work is beginning. Once we get the electrical and HVAC work done, then we will be able to start with drywall and insulation on the walls.
The interior of the performance space on our Hard Hat Tour Day.